| S.No. |
Report No.
|
Title
|
Month & Year |
| 1 |
BS-1 |
Investment for Coefficient of Dynamic Augment on Concrete Girder Bridges Test on Bridge No.54 Up (3 x 3.18.3m + 2 x 12.2m) on Godhra-Ratlam Section of W.Railway (B.G) |
Oct-1995 |
| 2 |
BS-2 |
Investigations for Dynamic Augment on Concrete Girder Bridges Test on Bridge No.162 (3x12.2m) and 163 (1 x 3.6m) on Goda-Gorakhpur Loop Section of N.E.Railway (M.G) (300 mm ballast cushion) |
March-1995 |
| 3 |
BS-3 |
Investigations for Dynamic Augment on Concrete Girder Bridges Test on Bridge No.54 (3 x 18.3m + 2 x 12.2m) on Godhra-Ratlam Section of W.Railway B.G (300 mm ballast cushion) |
March-1995 |
| 4 |
BS-4 |
Load Test of Arch Bridge No.23 (1 x 18.2 m) on Sagauli-Raxual Section on N.E.Railway MG |
Nov-1995 |
| 5 |
BS-5 |
Assessment of Residual Fatigue Life of Early Steel Wrought Iron Girder Bridges |
June-1995 |
| 6 |
BS-6 |
Load Test on MG Arch Bridge No.13 (1 x 4.83 m span ) on Aunrihar-Chappra Section of N.E.Railway for proposed retention other gauge conversion |
Oct-1995 |
| 7 |
BS-7 |
Investigation for Determining Coefficient of Dynamic Augment on Concrete Girder Bridge No.2/25576/7 at km.255/7 (2 x 26.226 + 3 x 10.0 m span) on Roha-Veer Section on Konkan railway |
Aug-1995 |
| 8 |
BS-8 |
Deflection Test on Betwa Bridge No.1086/1 (18 x 23.0 m) Welded Type Composite Span on Matatila-Basai Section of C.railway |
March-1998 |
| 9 |
BS-9 |
Report on Instrumentation of Rail-Cum-Road Bridge (17 x125m + 1 x 96.6m +2 x 30.26m over Brahmaputra River at Jogighopa) N.F.Railway |
July-1998 |
| 10 |
BS-10 |
Development of Vibration Signature Technique for Integrity Assessment of railway bridges (Model study on PSC Girder for Vibration performance) |
July-1998 |
| 11 |
BS-11 |
Application of Vibration Signature Technique on Plate Girder Railway Bridges |
Nov-2001 |
| 12 |
BS-12 |
Revised Report on Strategy for Quick Restoration of major bridge on Quazigund-Srinagar-Baramulla Section of N. Railway |
Sept-1998 |
| 13 |
BS-13 |
Report on Preventing Bird Menace in Buildings and Structures |
April-1999 |
| 14 |
BS-14 |
Durability of Concrete Structures
|
Jan-2001 |
| 15 |
BS-15 |
Report on Inspection of Bankim Setu ROB at Howrah |
April-1999 |
| 16 |
BS-16 |
Report on Preventing Unwanted Growth of Plants/Weeds in Buildings and Structures |
July-1999 |
| 17 |
BS-17 |
Water Proofing of Roofs |
Sept-1999 |
| 18 |
BS-18 |
Measurement of Longitudinal Forces on Elastomeric Bearings on Bridge No.23, Sawai-Madhopur, Jaipur Section, W. Railway to validate L.F.Disp Programme |
July-1999 |
| 19 |
BS-19 |
Report of Bridge Manual System |
Sept-1999 |
| 20 |
BS-20 |
Investigation for Dynamic Augment on Concrete Girder Bridges (test on Bridge No.627 between Nivasar and Ratnagari section of Konkan Railway) |
Dec-1999 |
| 21 |
BS-20-A |
Investigation on Cracks Developed in Beams of Manak Bhawan, RDSO, Lucknow |
Oct-1999 |
| 22 |
BS-21 |
Report on amenities to be provided at Railway Station and other public buildings for the persons with disabilities |
Oct-1999 |
| 23 |
BS-22 |
Report on Material for Railway Platform Surfacing |
Nov-1999 |
| 24 |
BS-23 |
Guidelines on use of Ready-mix Concrete
|
Aug-2000 |
| 25 |
BS-24 |
Report on Investigation for dynamic Augment on Ballasted Deck Concrete Bridges |
Dec-1999 |
| 26 |
BS-25 |
Guidelines on use of Admixtures in Concrete
|
Dec-1999 |
| 27 |
BS-26 |
Index of the report of the Bridge And Structures Standards Committee |
Dec-1999 |
| 28 |
BS-27 |
Report on Inspection on Bridge No.4 on proposed Phusro ? Jarandiah Division line on E.Railway |
April-2000 |
| 29 |
BS-28 |
List of current standard Drawings issued by Bridges and Structures Directorate ? Revision-10 |
April-2008 |
| 30 |
BS-29 |
Tunnels on Indian Railways (printed booklet) |
Sept-1998 |
| 31 |
BS-30 |
Important Bridges on Indian Railways (printed booklet) |
Jan-1999 |
| 32 |
BS-31 |
Impact Test on FRP Sleepers |
Nov-2000 |
| 33 |
BS-32 |
Study on Noise Level on Railway Bridges |
Dec-2000 |
| 34 |
BS-33 |
Effect of Vibrations due to Rail Traffic on Structures located along Railway Track |
March-2001 |
| 35 |
BS-34 |
Testing of Piers of Bridge No.1585 (9x12.2m G) on Badarpur-Silchar (MG) Section of N.F.Railway |
May-2001 |
| 36 |
BS-35 |
Development of cracks in the Channel Sleepers of Bridges No.184 (9 x 45.7m span girder) between Sahajanwa and Jagatbela Station on Gorakhpur-Lucknow BG route of N.E.railway |
May-2001 |
| 37 |
BS-36 |
Instrumentation Techniques to Monitor loss of Pre-Stress and Corrosion of Steel in Pre-Stressed Concrete |
June-2001 |
| 38 |
BS-37 |
Guidelines for Under Joint detailing using steel hollow section RHS/SHS in foot-over bridges (to be read with drawing No.CBS-0021/1-7)
|
Aug-2001 |
| 39 |
BS-38 |
Report on Suitability of Cement Grout for Corrosion Protection of Stay Cables of Cable Stayed ROB of Krishnarajapuarm (Bangalore) |
Aug-2001 |
| 40 |
BS-39 |
Guidelines for Assessment of Residual Fatigue Life of Early Steel/ Wrought Iron Girder Bridges |
Sept-2001 |
| 41 |
BS-40 |
Guidelines for Under Water Inspection of Bridges
|
Oct-2001 |
| 42 |
BS-41 |
Guidelines for Integrity Testing of Piles |
Oct-2001 |
| 43 |
BS-42 |
Guidelines on use of Micro Cover Meter |
Oct-2001 |
| 44 |
BS-43 |
Measurement of lateral displacement of girders of Bridge No.1248 (Balawali Bridge) of Moradabad Division on N.Railway |
Jan-2002 |
| 45 |
BS-44 |
An over view of revisions in IS:456-2000 Code of Practice for Plain and Rain Forced Concrete
|
Jan-2002 |
| 46 |
BS-45 |
Guidelines on Fabrication of Steel Channel Sleepers |
2004 |
| 47 |
BS-46 |
Report on Impact and static load tests on FRP Sleepers (Supplied by M/s Simba FRP Pvt.Ltd., Delhi) |
May-2002 |
| 48 |
BS-47 |
Report on Impact and Static Load Test on Synthetic Sleeper (developed by M/s Patail Group of Industries, Secunderabad
|
July-2002 |
| 49 |
BS-48 |
Guidelines for Inspection Maintenance and Rehabilitation of Concrete Bridges |
Sept-2002 |
| 50 |
BS-49 |
Report on Investigation of Sub-structures of Bridge No.445 (Dhawa Bridge) near Rafiganj on Mughalsarai Division of E.Railway |
Oct-2002 |
| 51 |
BS-50 |
Guidelines on use of Proformeter |
Dec-2002 |
| 52 |
BS-51 |
Guidelines on use of Acoustic Emission Technique on Railway Bridges |
Dec-2002 |
| 53 |
BS-52 |
Guidelines on use of Corrosion Monitoring Equipments |
March-2003 |
| 54 |
BS-53 |
Guidelines on use Ultrasonic Instrument for Monitoring of Concrete Structure. (Provisional). |
April-2003 |
| 55 |
BS-54 |
Testing of Bridge No.65 and 226 Up Acoustic Emission Technique |
June-2003 |
| 56 |
BS-55 |
NDT Testing of bridge No.1474, 1674 and T-7 in Mudurai Division of Southern Railway |
June-2003 |
| 57 |
BS-56 |
Preliminary investigation report of collapse of through girder of Bridge No.63 between Gevra road and Corva Section on Gevra Road Champa Section of S.E.C.Railway on 16/17-07-2003 |
July-2003 |
| 58 |
BS-57 |
NDT Report of bridge No.125 and 118-A in Jammu-Udhampur Section of Udhampur Division, N.Railway |
June-2003 |
| 59 |
BS-58 |
Report on impact and static load test on plastic recycled sleepers |
Sept-2003 |
| 60 |
BS-59 |
Report regarding collapse of footpath slab of road over bridge (Shastri bridge in Jabalpur division), W.C.Railway |
Nov-2003 |
| 61 |
BS-60 |
Non Destructive Testing of bridge on river Ganga (under construction) at Patna Danapur Division, E.C.Railway |
June-2004 |
| 62 |
BS-61 |
Non Destructive Testing of bridge No.355, 366, 388 and 390 on Mumbai Division, Western Railway |
Jan-2004 |
| 63 |
BS-62 |
4 Nos. of PSC girder bridges on Singrauli-Obra Section of E.C.Railway
|
March-2004 |
| 64 |
BS-63 |
Causes, Evaluation and repair of cracks in concrete |
March-2004 |
| 65 |
BS-64 |
Collapse of FOB at Km.48/12-11 between THAKURLI-DOMBIVLI (Mumbai Division), Central railway |
April-2004 |
| 66 |
BS-65 |
Non Destructive Testing of bridge No.73 on Mumbai Division, Western Railway |
April-2004 |
| 67 |
BS-66 |
Non Destructive of bridge No.1066 and 1107 on Roha-Manglore Section of Konkan Railway |
June-2004 |
| 68 |
BS-67 |
Non Destructive of road over bridge No.236-A on Dhanbad-Gaya Section of Dhanbad Division of E.C.Railway |
June-2004 |
| 69 |
BS-68 |
Non Destructive Testing of Bridge No.123, 144, 157, 232, 242 on Cuttack-Paradep Section on Khurda Road Division of E.Co.Railway |
Nov-2004 |
| 70 |
BS-69 |
Non Destructive Testing of PSC Slab No.92 of Lucknow Division N.Railway |
Dec-2004 |
| 71 |
BS-70 |
Assessment of Residual Life of Ganga Bridge No.110 Dn, (near Kanpur), Lucknow Division, N.Railway |
Dec-2004 |
| 72 |
BS-71 |
Condition assessment of PSC girder Bridge No.73 over Vasai Creek on Mumbai-Surat Section of Western Railway |
March-2005 |
| 73 |
BS-72 |
Non Destructive Test on Bridge No.78 and 78-B of Sonpur Division, E.C.Railway |
May-2005 |
| 74 |
BS-73 |
Non Destructive Test on Bridge No.52 and 53 of Samastipur Division, E.C.Railway |
June-2005 |
| 75 |
BS-74 |
Non Destructive Testing of Road over Bridge (under construction) at Patna, Danapur Division, E.C.Railway |
July-2005 |
| 76 |
BS-75 |
Assessment of Residual Life of Ganga Bridge No.110 Dn (Near Kanpur), Lucknow Division, N.Railway |
Aug-2005 |
| 77 |
BS-76 |
Recent Advances In Seismic Design Criteria Of Bridges |
Report not published. |
| 78 |
BS-77 |
Assessment of Residual Life of Structure of Bridge No.95211 Narmada Bridge near Jabalpur |
Jan-2006 |
| 79 |
BS-78 |
Non Destructive testing on proposed Headquarter Building, N.C.Railway |
Feb-2006 |
| 80 |
BS-79 |
Assessment of Residual Life of Girder of Bridges No.73 and 75 (abandoned) Vasai Creek Bridge on Borival-Virar section of Western Railway |
May-2006 |
| 81 |
BS-80 |
Guidelines for design of POT-PTFE Bearing for Railway Bridges |
Sept-2006 |
| 82 |
BS-81 |
Condition assessment of 3rd. Godavari bridge near Rajamundary, S.C.Railway |
Nov-2006 |
| 83 |
BS-82 |
Guidelines on Use of Core Cutter and Other Miscellaneous Tools on Railway Bridge |
Nov-2006 |
| 84 |
BS-83 |
Non Destructive Testing Newly construction Station Building Rewari, Jaipur Division |
Feb-2007 |
| 85 |
BS-84 |
Assessment of Residual Life of Girder of Bridge No.531 Dn (Son Bridge) near Dehari-On-Sone E.C.Railway |
May-2007 |
| 86 |
BS-85 |
Monitoring Report of Bridge on Operation of BOXEN Wagons Loaded up to CC + 8t 2t/CC+62t as pilot project on Identified Routes |
May-2007 |
| 87 |
BS-86 |
Non Destructive Testing of Road over Bridge No.61A on Hissar- Bhatinada Section of N.W.Railway |
Nov-2007 |
| 88 |
BS-87 |
Non Destructive Test on Newly Constructed Headquarter Building , Allahabad, N.C.Railway |
March-2008 |
| 89 |
BS-88 |
Technical Literature on corrosion/carbonization protection in concrete structures |
March-2008 |
| 90 |
BS-89 |
Guidelines for the use of High Performance Concrete in Bridges |
March-2008 |
| 91 |
BS-90 |
Study of probable cause of cracks in different members and assessment of Residual Fatigue Life of Bridge No.46 Up/ Mid Line near Bilaspur |
April-2008 |
| 92 |
BS-91 |
Guidelines for Assessment of Residual Fatigue Life of Steel Girder Bridges |
May-2008 |
| 93 |
BS-92 |
Measurement of Vibration of the Piers of the Bridges Nos.9 and 7 on Gorakhpur-Panihawa Section of N.E.Railway |
May-2008 |
| 94 |
BS-93 |
Condition Assessment of the Piers of Bridge No,133, 165 and 263 on Hassan-Manglore section of S.W.Railway |
June-2008 |
| 95 |
BS-94 |
Non Destructive Test on newly constructed DRM Office Building at Agra Cantt. N.C.Railwa`y |
July-2008 |
| 96 |
BS-95 |
Assessment of Residual Life of Girders of Bridge No.5A Up/Dn (Setlej Bridge), near Ludhiana |
July-2008 |
| 97 |
BS-96 |
Guidelines on Under Water Inspection of Bridges |
July-2008 |
| 98 |
BS-97 |
Assessment of Residual Fatigue Life of Girders of Bridge No.1554 UP near Vijianagram, East Coast Railway |
Oct-2008 |
| 99 |
BS-98 |
Inspection of Bridge No.49, Asansol Division, Eastern Railway by RDSO |
Dec-2008 |
| 100 |
BS-99 |
Inspection of Bridge No.178, Ajmer Division, North Western Railway by RDSO |
Feb-2009 |
| 101 |
BS-100 |
Monitoring Report of Bridges on Operation of BOXN Wagons Loaded up to CC+8+2t/CC+6 + 2t as Pilot Project on Identified Routes |
May-2009 |
| 102 |
BS-101 |
Non Destructive Testing of Road over Bridge in lieu of level crossing No.27 at Etawah, Allahabad Division, N.C.Railway. |
July-2009 |
| 103 |
BS-102 |
GUIDELINES FOR INSPECTION & MAINTENANCE OF BRIDGE BEARINGS |
September, 2009 |
| 104 |
BS-103 |
GUIDELINES ON NON-DESTRUCTIVE TESTING OF BRIDGES |
August, 2009 |
| 105 |
BS-104 |
GUIDELINES ON USE OF ACOUSTIC EMISSION TECHNIQUE (AET) ON RAILWAY BRIDGES |
OCTOBER- 2009 |
| 106 |
BS-105 |
GUIDELINES ON PIPE LINE CROSSINGS UNDER RAILWAY TRACK |
Novemeber-2012 |
| 107 |
BS-106 |
BROAD GUIDELINES FOR INSTRUMENTATION OF BRIDGES FOR RUNNING HIGHER AXLE LOADS |
April, 2010 |
| 108 |
BS- 108 |
Monitoring Report of Bridges On Operation of BOXN Wagons Loaded up to CC+8+2t/ CC+6+2t As Pilot Project on Identified Routes |
May2010 |
| 109 |
BS-109 |
DESIGN AND QUALITY AUDIT REPORT ON LANDSLIDE AND FAILURE OF RETAINING WALL BETWEEN RATNAGIRI-NIVSAR STATIONS ON RATNAGIRI-MADGAON SECTION OF KRCL |
JULY- 2011 |
| 110 |
BS-110 |
GUIDELINES FOR FABRICATION OF STEEL GIRDER PROCEDURE IN WORD |
December-2011 |
| 111 |
BS-111 |
Guidelines for use of High Strength Friction Grip (HSFG) bolts on bridges on Indian Railways |
June 2012 |